Last phase of light rail platform retrofit

After month and a half of construction, Blossom Hill and Cottle stations will reopen on Friday, September 26. Construction at Santa Teresa and Snell stations, the last two remaining, will start on Monday, September 29.

At Santa Teresa, passengers will board and exit on a temporary platform during the construction. At Snell, the station will be closed and no bus bridge will be provided (because Snell is less than a mile away from Blossom Hill). However, line 66 will still go into the station during construction.